Emergency Response Plan Drill Report
Category: News and Information
Time:May 21,2026
I. Drill Objectives
2.To strengthen employees' awareness of the risks of titanium tetrachloride leakage (fuming on contact with water, highly corrosive, toxic) and improve capabilities in initial response, alarm reporting, evacuation, leak sealing, personal protection, decontamination, and environmental treatment.
1.To test and improve the Emergency Response Plan for Titanium Tetrachloride Leak Accidents and the Environmental Emergency Response Plan, identify deficiencies in the plans, and close out corrective actions.
3.To clarify the responsibilities of each emergency team and the coordination procedures, and test the collaborative efficiency of command, communications, supplies, medical response, environmental protection, and emergency repair.
4.To verify the integrity and availability of emergency supplies, equipment, and protective gear so as to meet practical requirements.
5.To implement the new 2026 emergency drill regulations: de-scripted, hands-on, strong closed-loop management, assessable, and fully documented.
II. Drill Time and Location
●Time: 15:00–15:40 on May 19, 2026 (including a 10-minute review session)
●Location: the No. 2 titanium tetrachloride storage tank area of the hydrolysis tank farm and its surrounding cordoned area, the wastewater pretreatment area, and the temporary first-aid station
III. Drill Type and Level
●Type: Special emergency drill (leak + fire risk + environmental protection)
●Level: General accident (Level IV)
●Format: Semi-blind drill (the leak type is announced in advance, but not the specific time, leak volume, wind direction, or secondary risks), meeting the 2026 practical-combat requirements.
IV. Risk Overview (Titanium Tetrachloride)
●Highly corrosive; reacts violently with water, generating hydrogen chloride white fumes, heat, and corrosive liquid;
●Inhalation/skin contact can cause burns and poisoning; a leak can easily contaminate soil and water bodies;
●Scenario simulated this time: aged DN50 outlet flange gasket on the No. 2 storage tank plus rusted and loosened bolts, causing a medium leak accompanied by white fumes and a small amount of liquid accumulated on the ground.
V. Organization and Responsibilities
(1) Emergency Command Center
●Chief Commander: Fan XiaokuiResponsibilities: overall on-site command; issuing start/termination orders; deciding on the leak-sealing plan; directing evacuation and cordoning; external liaison; approving review findings and corrective actions.
●Deputy Chief Commander: Xu Haiying, Workshop DirectorResponsibilities: assisting in command; personnel/supplies coordination; on-site safety supervision; information transmission; supervision of environmental treatment.
(2) Emergency Teams and Division of Duties
1.Alarm & Communications Team (2 members): raise the alarm and escalate at the first moment, liaise with all teams, and record key time nodes.
2.Cordon & Evacuation Team (3 members): set up cordon tapes and warning lines, evacuate upwind, count personnel, and keep unauthorized persons out.
3.Leak Sealing & Repair Team (4 members, led by Liu Chengang): wear heavy-duty chemical protective suits, gas masks, and corrosion-resistant gloves; close valves to cut off material flow, locate the leak point, replace the gasket and bolts, and clean up residues.
4.Protection & Decontamination Team (2 members): distribute protective equipment, guide proper donning, decontaminate personnel, flush contaminated areas, and divert waste liquid into the sewage pool.
5.Environmental Treatment Team (2 members): lay impermeable barriers, absorb residues with sand, divert titanium-bearing wastewater into the emergency pool, and monitor white-fume dispersion.
6.Medical Rescue Team (2 members): set up a temporary first-aid station, provide first aid for burns/poisoning, transport casualties by stretcher, and contact external medical services.
7.Logistics Support Team (2 members): distribute supplies, provide emergency lighting, tool support, and on-site power supply.
8.Evaluation & Recording Team (2 members, Safety Department): record audio/video throughout, keep timing, document key time nodes, conduct on-site evaluation, fill in the evaluation form, and organize the review session.
VI. Participants
The emergency command center, the emergency rescue and repair team, all employees of the hydrolysis workshop, warehouse keepers, safety management personnel, and evaluation and recording staff.
VII. Drill Supplies and Equipment List
●Protection: heavy-duty chemical protective suits, positive-pressure self-contained breathing apparatus (SCBA)/gas masks, acid- and alkali-resistant protective boots, corrosion-resistant gloves, protective goggles
●Leak sealing & repair: wrenches, new flange gaskets, stainless-steel bolts, leak-sealing clamps, exhaust/extraction device, toolbox
●Cordon & evacuation: cordon tape, warning signs, megaphones, personnel counting sheets
●Environmental treatment: sand, shovels, impermeable sandbag barriers, decontamination hoses, guide channels to the sewage pool
●Medical rescue: first-aid kit, stretcher, decontamination solution, burn treatment supplies
●Communications & recording: walkie-talkies, mobile phones, voice recorders, video cameras, timers, drill evaluation forms, sign-in sheets
VIII. Drill Scenario Setting (Semi-Blind Drill)
Scenario: At 15:00 on May 19, 2026, an employee on batch-feeding duty in the hydrolysis workshop discovered during inspection that a large amount of white fumes was escaping from the DN50 outlet flange at the bottom of the No. 2 titanium tetrachloride storage tank, and pale-yellow corrosive liquid was flowing on the ground. The flange bolts were rusted and the gasket had loosened; the leak continued and white fumes spread, posing risks of personnel burns, poisoning, and environmental pollution.
IX. Drill Steps (with Time Nodes, Assessable)
(1) Discovery and Alarm (0–2 minutes)
1.15:00 Zhang Bixin, on batch-feeding duty, discovered the leak and white fumes during inspection, immediately stopped work, and evacuated to a safe area on the upwind side.
2.15:01 Reported the alarm to the chief commander by phone/walkie-talkie: "Leak at the bottom flange of the No. 2 titanium tetrachloride storage tank; white fumes and accumulated liquid observed. Requesting support!"
3.15:02 After confirmation, the chief commander activated the company's special emergency plan for leaks, notified all teams to be in place, and issued the orders of "cordon, evacuation, leak sealing, decontamination, and environmental treatment."
(2) Cordon and Evacuation (2–5 minutes)
1.The cordon team arrived on scene, demarcated the leak zone, danger zone, and safe zone, set up cordon tapes and warning signs, and kept unauthorized persons out.
2.The evacuation team guided workshop personnel to evacuate upwind to the assembly point on the upwind side, counted personnel, and confirmed that no one was left behind.
3.Evaluation points: alarm raised within ≤1 min; evacuation completed within ≤3 min; cordon in place within ≤5 min.
(3) Protection in Place and Site Control (5–8 minutes)
1.The decontamination team distributed protective equipment; the repair team properly donned heavy-duty chemical protective suits plus SCBA and, after inspection and confirmation that everything was correct, entered the danger zone.
2.The logistics team ensured lighting and smooth communications; the environmental team laid impermeable barriers and prepared sand.
(4) Valve Closing, Material Cut-off and Leak Sealing (8–25 minutes)
1.The repair team entered the site, closed the bottom valve of the No. 2 storage tank, and cut off the material source.
2.Investigation confirmed that the rusted flange bolts and the aged, loosened gasket were the leak points.
3.The residual material in the pipeline was drained; a new gasket and new stainless-steel bolts were installed and evenly tightened, completing the leak sealing.
4.The exhaust team started the exhaust device to capture and treat the hydrogen chloride white fumes, reducing the dispersion risk.
5.Evaluation points: initial response within ≤5 min; leak sealing completed within ≤20 min; standardized operations; no secondary leakage.
(5) Residue Cleanup, Decontamination and Environmental Treatment (25–32 minutes)
1.The environmental team absorbed floor residues with sand, which were then collected and disposed of as hazardous waste.
2.The decontamination team flushed the contaminated area with large amounts of clean water; all titanium-bearing wastewater was diverted into the emergency pool/sewage pool, with external discharge strictly prohibited.
3.Monitored the dispersal of white fumes; no residue remained on the ground and no overflow pollution occurred.
(6) Medical Rescue (Throughout the Drill)
●One employee was simulated as slightly burned; the rescue team performed wound flushing, disinfection, and bandaging, and made preparations for transport.
(7) End of Drill (32–35 minutes)
1.The chief commander confirmed that the leak had been stopped, the site was safe, there were no casualties, and the pollution was under control, and declared the drill over.
2.Personnel withdrew, the cordon was lifted, and supplies were sorted and stored.
(8) Review and Evaluation (35–40 minutes, Key to Closed-Loop Management)
1.The evaluation team reported the time nodes, operational highlights, and existing problems (classified as Level I/II/III deficiencies).
2.All personnel discussed the deficiencies and clarified the responsible persons and deadlines for rectification: Level I (72 h), Level II (15 d), Level III (30 d).
3.Within 30 days, the Safety Department revised the plan, updated the response cards, and improved the supplies ledger, forming a closed loop.
X. Evaluation Criteria (per GB/T 46792—2025)
1.Alarm response: ≤1 min
2.Evacuation completed: ≤3 min
3.Initial response (valve closing): ≤5 min
4.Leak sealing completed: ≤20 min
5.Protective donning: 100% standardized, no violations
6.Recording and documentation: full audio/video coverage, complete time nodes, complete evaluation forms
7.Closed-loop rectification: 100% of problems rectified; plan revised in time
XI. Safety Precautions
1.A drill is not a real emergency. Real contact with the leaked material is strictly forbidden; wear protective equipment and follow instructions.
2.Crossing the cordon area, lingering in the wind path, and removing protective equipment are strictly prohibited.
3.If a real emergency occurs during the drill, terminate the drill immediately and give priority to handling the real accident.
4.Smoking and open flames are prohibited on site; ensure smooth communications.
XII. Document Archiving (Retained for ≥3 Years)
●Drill plan, sign-in sheets, supplies list, audio/video records, evaluation forms, review minutes, rectification ledger, and plan revision records.